How a Willow Remodel Runs, Week by Week

A bathroom remodel with us takes two to three weeks on site and a kitchen four to six, under CSLB license #1127360. Every job follows the same five steps.

Call (650) 507-4525 Get an Estimate

Same week you call

1. Site visit

What you do
Show us the room and tell us what bothers you about it. Photos of rooms you like help.
What we do
Measure, look behind what we can (access panel, crawlspace, slab), and talk through which package fits.
What can slip
Nothing, usually. Weekends book up first.

Within 48 hours of the visit

2. Written fixed-price estimate

What you do
Read it, ask questions, compare it with the others you have.
What we do
Itemize every line the way our cost pages do, with allowances shown. The price holds for 30 days.
What can slip
Large or unusual jobs can take an extra day or two to price properly; we tell you if so.

1–2 weeks

3. Design and selections

What you do
Choose tile, fixtures, vanity or cabinets and counters, with our help or your designer’s.
What we do
Check every selection for size, compatibility and lead time, then order before we open the room.
What can slip
Special-order tile and custom cabinets. We will not start demolition until they are confirmed.

Depends on the city; we pull it

4. Permit

What you do
Sign the owner authorization if the city asks for one.
What we do
Prepare drawings and forms, submit, answer plan-check comments and schedule inspections.
What can slip
City review times. Each city page lists what to expect there.

Bathroom 2–3 weeks · kitchen 4–6 weeks

5. Build

What you do
Clear the room and the path to it. Keep pets and kids out of the work area.
What we do
Protect floors, demolish, rough in, pass inspection, waterproof and flood-test, tile, install, clean daily, and send a short update every evening. Final walk-through and warranty at the end.
What can slip
Hidden damage behind walls. If we find it, we stop, show you and price it in writing before fixing it.

The build, day by day

Hall bathroom, about 3 weeks (15 working days)
Demolition, framing fixes Rough plumbing and electrical, inspection Waterproofing, 24-hour flood test Tile Vanity, fixtures, paint Glass, final inspection, walk-through Day 1 Day 15
Full kitchen, about 6 weeks (30 working days)
Demolition Rough plumbing and electrical, inspection Drywall and paint Cabinets Countertop template and install Backsplash, appliances, final Day 1 Day 30

Working days, Monday to Saturday, after materials are on site. Inspections are scheduled by the city and can shift a step by a day or two.

Get a written estimate in 48 hours

Tell us about the room. We visit the same week, measure, and send a written, itemized estimate within 48 hours.